Update - Gas Works in Craiglockhart Avenue
Added on 04 December 2024
Information provided 4th December by City of Edinburgh Council
The latest news is that the gas mains replacement scheme is currently running approx. 2 weeks behind schedule on Craiglockhart Avenue. It is believed that this will mean works will now continue along Colinton Road in the New Year. There is one other part of the scheme remaining after this on Lanark Road and it is hoped that the team are able to move from Colinton Road to Lanark Road at some point in early February.
Click here for News item showing the original dates for the work.
And the following receivedfrom SGN on 10th Dec
Our critical project in the Craiglockhart area is progressing well, however due to some unexpected engineering difficulties, our work has been slightly delayed, and we are a few weeks behind schedule.
We're sorry for the inconvenience this is causing, but ensuring everyone's continued safety is our number one priority and we're working as quickly as we can.
We are currently working to complete phase three of our project in Craiglockhart Avenue before Christmas. We'll provide a further update on our progress next week.
Phases four and five of the Craiglockhart section of our project will now commence in the New Year.