GAS WORK in Craiglockhart Avenue & Lanark Road

Added on 06 October 2024

We have today received the following from the Roads Coordination Engineer – South West Area, City of Edinburgh Council. 

"Please see below information from SGN in relation to a forthcoming gas mains replacement scheme to be undertaken in the forthcoming weeks on Craiglockhart Avenue and the surrounding area.

Work on this project will commence promptly due to a large number of gas escapes identified on the main road in the past year. As such the timetable for this scheme has been brought forwards with the approval of the CEC Roads Coordination team. 

You will note that the scheme has been split up into different phases where traffic will be managed in different methods suitable to the engineering needs and conditions of each road.

Part 1 Craiglockhart - 14th October

Phase 1 We’ll kick off the project off the main road within Redhall House Drive with a road closure on Craiglockhart Drive South. Approx. 1 week (14/10/2024)

Phase 2 3 way lights will be in place on Lanark Road junction with Craiglockhart Avenue. Approx. 3 weeks (21/10/2024)

Phase 3 Craiglockhart Avenue will become a one way system with traffic restricted northbound diverting traffic through Ashley Terrace. Bus routes 4 & 36 are affected by the diversion. Approx. 3 weeks (11/11/2024)

Phase 4 4 way Lights will be in place on Colinton Road junction with Craiglockhart Avenue. Approx 2 weeks (02/12/2024)

Phase 5 Lane closures along Colinton road will be place, temp bus stops will be erected when required. Approx 3 weeks (16/12/2024)

Part 2 Lanark Road January 2025

Phase 1 3 Way traffic lights will be in place on Lanark Road junction with Kingsknowe Road South. Approx. 1 week (20/01/2025)

Phase 2 3 Way lights will be in place on Lanark Road junction with Dovecot Park, along with a road closure in Kingsknowe Park. Approx. 1 week (27/01/2025)

Phase 3 Road Closure on Kingsknowe Drive. Approx. 1 week (03/02/2025)

Phase 4 3 Way traffic Lights will be in place on Lanark Road junction with Dovecot Grove, along with a road closure in Arnott Gardens. Approx. 1 week (10/02/2025)

Phase 5 Lane Closure. Approx. 1 week (17/02/2025)

Phase 6 Parking suspensions within Redhall View. Approx. 1 week (23/02/2025)

SGN has today (2/10/24) sent the above information including a map which can be seen here.

 

^